Swanston Street MSB & Mains Upgrade
Project Date
2023
Location
Melbourne, Victoria
Client brief
Following a flood caused by the fire services system, the basement Main Switchboard (MSB) was inundated and damaged beyond repair. National Operations Network was engaged to replace the site MSB and associated electrical infrastructure, restore power safely, and upgrade the installation to meet current standards.
Project Scope
- Upgrade and connection of consumer mains from the substation to the MSB
- Installation of new MSB, public light and power switchboards
- New submains from MSB to DBs and take-off boxes
- Joining and testing of MIMs/pyro cabling
Project Value $250K+